Trump’s Official Memecoin Surges Despite Massive $320 Million Unlock in Thin Holiday Trading Slovenia Moves to Tax Crypto Profits at 25% Unpacking the DOJ’s Crypto Enforcement Memo Canary Capital Files for Tron ETF With Staking Capabilities Feds Mistakenly Order Estonian HashFlare Fraudsters to Self-Deport Ahead of Sentencing CoinDesk Weekly Recap: EigenLayer, Kraken, Coinbase, AWS The Case for User-Owned AI Crypto Exchange Kraken Launches FX Perpetual Futures, Offers 24/7 Trading in Forex Majors Friends With Benefits Grows Up KiloEx’s ‘Sophisticated’ Hack Shows DeFi Risks — But This Time, Recovery Was Swift

Bitdeer Buys 101 MW Gas Power Plant in Alberta, Canada for BTC Mining

Bitcoin (BTC) mining company Bitdeer announced today that it had acquired a 101-MW gas-fired power plant near Fox Creek, Alberta, to build a “vertically integrated” BTC mining operation.

“We are really excited about planting roots in Alberta, our first site in Canada. This acquisition is the culmination of extensive collaboration with multiple government agencies and the Canadian Blockchain Consortium,” Haris Basit, chief strategy officer at Bitdeer, said in a press release. “It marks a significant step in our strategy to become the first fully-vertically integrated Bitcoin miner, giving us unmatched control over costs, energy efficiency, and scalability.”

Bitdeer says they plan to build out a 99 MW datacenter on the site. The site has the capacity to scale to 1 GW. Energy production costs for the facility will be between $20 to $25 per MW/h.

The plant is also licensed for a 99 MW interconnect to the local power grid, and Bitdeer said it plans to sell power back to the Alberta grid to stabilize prices during periods of high demand.

“By combining our own power generation, SEALMINER mining machines and opportunistic grid participation, we believe this site will set a new benchmark for industry unit economics,” Basit added.

Bitdeer says it plans to commence site preparation and initial infrastructure development in Q2 2025 and have it fully operational in Q4 2026.